Texas records two more Nexus data center registrations near Hubbard
The Apex HB3 and HB4 filings list 982,756 square feet of planned floor area combined. Each gives an estimated construction cost of $400 million and an estimated completion date of January 5, 2028.
The Texas Department of Licensing and Regulation has recorded two more data center buildings at the Nexus campus near Hubbard, Texas, in its accessibility database. The Apex HB3 registration and the Apex HB4 registration both list Nexus Data Centers Hubbard, LLC as the owner.
The two filings document 982,756 square feet of planned floor area. They join the Nexus - Apex DFW HB1 registration and the Nexus Apex HB2 registration at the same address, bringing the number of data center buildings in the state’s records for the site to four.
Both new filings describe data center construction and site improvements at 357 HCR 3372 in Hill County. Nexus says the campus lies outside Hubbard city limits. Registered projects in the state’s accessibility system generally undergo plan review before inspection.
Each new filing lists 491,378 square feet. The filings give no power capacity for either building. Each puts the estimated construction cost at $400 million and the estimated completion date at January 5, 2028.
More news

Datlantis reports at-sea tests of underwater data center prototypes

U.S. Army requires power generation for data center bids at nine sites

KT Cloud commits to full capacity at Keppel’s Ansan data center