Ohio board approves 800 MW gas plant for EdgeConneX data center
PowerConneX would supply the proposed campus in Pickaway County directly, without a grid connection. The approval carries 41 conditions.
The Ohio Power Siting Board approved PowerConneX’s 800 MW Ashville Energy Center, a natural gas plant in Pickaway County, Ohio. The board said the plant would supply the adjacent EdgeConneX data center directly and operate without a connection to the electric grid, an arrangement called behind-the-meter generation.
The plant’s 800 MW generating capacity is separate from the data center’s IT capacity. The board said its decision covers the plant and that the data center is outside its jurisdiction. The Supreme Court of Ohio described EdgeConneX’s plans for two data center buildings on the same property.
PowerConneX plans to build the plant on 110 acres along State Route 752, east of State Route 23 in the village of Ashville.
In case 26-196-EL-BGN, the board adopted and revised an agreement among PowerConneX, the village and board staff. The board said the approval’s 41 conditions are intended to limit impacts during construction and operation. The approval also requires PowerConneX to honor its financial commitments to the Ashville community.
More news

FCC grants conditional approval for up to 1 million SpaceX data center satellites

Senate Banking Committee schedules December 3 export controls hearing with Jensen Huang

Malaysia plans to advise data centers against serving seven entities on the U.S. Entity List