Microsoft seeks permit for five-building Virginia data-center campus
Microsoft's LVL 16 permit application remains under review in Virginia, while reported federal plans describe five data-center buildings on 316.7 acres.
Microsoft has applied for a Virginia Water Protection individual permit for a data-center project called LVL 16 in Mecklenburg County. The state permit record identifies Microsoft Corporation as the applicant and lists the application as in progress, not as a construction approval.
Data Center Dynamics reported that the linked federal application describes five single-story data-center buildings across 316.7 acres on three parcels near Boydton. The federal notice was inaccessible during research, so those details could not be independently confirmed from that notice.
The outlet places the proposed site north of Phillis Road, east of Rose Hill Road and south of the Tobacco Heritage Trail. It says the plans also include an electrical substation, water storage, domestic and fire-hydrant water systems, sanitary sewer and industrial wastewater systems, fiber and electrical conduit, stormwater conveyance and detention ponds.
The application’s stated purpose, according to the report, is to add cloud-storage and computing capacity to meet regional demand. The available sources do not give the project’s planned electrical capacity, cost, construction start or completion schedule.
Virginia’s portal shows that the Department of Environmental Quality began reviewing the application on July 21 and started developing a draft permit decision on October 26. The latter step remains in progress. The portal lists applicant review of a draft, the state’s draft-permit public-comment step and the final permit decision as not started.
Data Center Dynamics reported that a separate federal comment process is further along, with the U.S. Army Corps of Engineers’ Norfolk District accepting comments through December 19. That reported federal period is distinct from Virginia’s draft-permit comment stage. The filing and pending reviews do not establish that construction has been approved or begun.