TeraWulf says Kentucky campus moves into vertical construction

TeraWulf says structural steel is going up at its Justified Data campus in Kentucky, while its 401 MW Anthropic lease remains targeted for phased delivery from late 2027 through the second quarter of 2028.

D
Nov 20, 2026 · 1 min read

TeraWulf says the first structural steel is going up at its Justified Data campus in Hawesville, Kentucky, moving the three-building project planned for Anthropic from foundation work into vertical construction. The campus is intended to supply about 401 megawatts of critical IT load, but none of that leased capacity is established as operational.

In a project update, TeraWulf said crews had driven more than half of the foundation piles and that structural steel for the first building had mostly been delivered and staged. The company said substantial steel deliveries had also been made for the second building. Those physical-progress details are TeraWulf’s claims; the available record does not include an independent site inspection confirming them.

The steel work is a new milestone, not the start of the overall build. A Nov. 6 investor update already described construction as underway across the campus. Fluor also said early works had begun under its engineering, procurement and construction contract for all three data center buildings.

TeraWulf’s Nov. 4 filing says the leases run for 20 years and cover CB-1, CB-2 and CB-3. The company expects delivery to begin in late 2027 and finish in the second quarter of 2028. Its investor update assigns target delivery dates of the fourth quarter of 2027 for CB-1, the first quarter of 2028 for CB-2 and the second quarter of 2028 for CB-3. Those dates remain company targets rather than completed deliveries.

The 401 MW figure refers to computing equipment load, not the site’s total utility draw. TeraWulf’s quarterly filing says the Kentucky Public Service Commission approved up to 482 MW of electric service for the campus.