XTX Markets opens its first data center in Kajaani, Finland
XTX Markets says it moved computing equipment for deep learning from leased space to a site with 22.5 megawatts of IT power capacity. The company says power for its third facility remains uncertain.
XTX Markets announced on November 24 that it had opened its first company-owned data center in Kajaani, Finland. XTX says the site has 22.5 megawatts of IT power capacity, the power available to computing equipment.
XTX says it previously ran its computing cluster in leased data centers across Europe and moved computing and storage equipment to Kajaani. The firm says it uses deep-learning models to forecast prices for financial instruments. In one six-week stretch, XTX says it moved 417 petabytes of storage capacity from a leased site five kilometers away.
XTX says it has secured electricity supply and grid connections for its first two Kajaani facilities. The company says power for the third facility, now under construction, remains uncertain, citing delays in permits needed to acquire rights for power lines.
The Finnish Permit and Supervision Agency lists XTX’s proposed 400-kilovolt transmission line as pending on its environmental assessment page. The line would connect the Kajaani campus to a substation in Otanmäki. The agency’s August 7 environmental assessment opinion says the line requires a permit to acquire rights along the route.
XTX Chief Operating Officer Mike Irwin said the company had invested more than €400 million in construction by the opening. Contractor YIT put its main construction contract for the first facility at about €100 million in December 2024.
XTX expects the second facility to start operating in 2027 and is targeting mid-2028 to finish building the third.